On NFPA 99, 1999 edition shows: Section 4.3.1.2.10 (.2) & 4.3.1.12
Qualified Competent Technician & Brazing Procedure Performance. Page #50
On NFPA 99, 2005C Section 5.1.10.11 / 5.1.10.10.11.2 & 5.1.10.10.12
Qualified Competent Technician & Brazing Procedure Performance Page #39
On NFPA 99, 2015 Section 5.1.10.11.10.1(.2) / 5.1.10.11.11
Qualified Competent Technician & Brazing Procedure Performance. Page #49,50
The Inspection and testing shall include all components deemed to be breached are subject to verifier inspection and testing, that includes upstream for vacuum system and downstream for pressure gases at the point or area of intrusion. Inspection and testing report shall be submitted to the facility authority.
NFPA 99,2005 edition, sections 5.1.12.1.2
NFPA 99, 2015 edition, section 5.1.12.1.2
Acceptance of verifier report shall be permitted to satisfy requirements of 5.1.12.1.10.